Ministry of Environment, Sri Lanka · GEF ID: 10552 (FSP · 48 Months) · IUCN / CBSL / DCS

GEF-7 Coastal & Marine Natural Capital Accounting Console

Integrated project planning, parliamentary vote treasury control (Head 160), multi-agency procurement compliance, and UN-SEEA / PES monitoring.

Pilot Site · 4 DSDs · 6 Protected Areas incl. Bar Reef MPA
Governance Role Perspective
Month 24 / 48
Mid-Term Operational Snapshot
Project Director Briefing Monitoring Puttalam pilot execution: SPI at 0.94 requires hydrological restoration acceleration in Mundel–Kalpitiya prior to MTR.
MTR Readiness: 84%
Total Seascape Area
294,822 ha
131,615 ha Terrestrial · 163,207 ha Marine
Total Seascape Budget
$8.46M
LKR 2.54B (GEF $1.17M + Co-Fin $7.29M)
2027 Appropriation Vote
LKR 534.70M
Head 160-02-04 · FS 11 & FS 12
EVM Portfolio Health
SPI 0.94 · CPI 1.02
Schedule Slight Delay · Under Budget On Cost Target

48-Month Lifecycle S-Curve (PV, EV & AC)

Cumulative USD · GEF STAR Allocation ($1,174,000 BAC)
Vertical marker tracks the active Reporting Cycle month. Drag the simulator slider above to forecast variance trajectories through Month 48.

Sri Lanka Project Seascapes

8°10'40.74"N · 79°47'9.72"E
Puttalam Active
SE Palk Bay (Mannar) Trincomalee Puttalam Pilot Madu Ganga–Hikkaduwa
Divisional Secretariat Divisions (ha)
DSD / Zone Area (ha) Share

Blue Carbon & Coastal Ecosystem Assets

IUCN / Ramsar Baseline

Role-Filtered Governance Action Queue

Project Director

Work Breakdown Structure & Earned Value Management Engine

4-Level Hierarchy (Component → Outcome → Output → Activity) · Critical Path & 48-Month Gantt
BAC (GEF STAR)
$1,174,000
Puttalam Baseline
Planned Value (PV)
$598,153
50.9% Planned
Earned Value (EV)
$559,998
47.7% Complete
Actual Cost (AC)
$550,100
46.9% Disbursed
Variances (SV / CV)
−$38k / +$10k
SPI 0.94 · CPI 1.02
Forecast EAC
$1,153,261
VAC: +$20,739
WBS Work Package / Activity Agency BAC ($) Complete Status / CP 48-Month Gantt Timeline (M1–M48)
Click any Level-4 activity row to inspect deliverables, physical targets, and update progress %.

Government Treasury Management (Head 160-02-04) & PFM

Ministry of Environment · Programme 02: Development & Natural Resource Management · Project 04
CIGAS Monthly Posting: Verified (FR 135 / FR 394)
2027 Parliamentary Vote
LKR 534.70M
Appropriation Act Head 160-02-04
FS 11 · GOSL Consolidated
LKR 312.40M
58.4% · Counterpart & Recurrent
FS 12 · Foreign Grant (GEF)
LKR 222.30M
41.6% · Reimbursable / Imprest
YTD Vote Utilisation
LKR 268.42M
50.2% Expended + Committed

Object Code Allocation & Expenditure Ledger

Dual-Financing Breakdown (FS 11 vs FS 12)
Code Object Description Source Vote (M) YTD Exp (M) Commit (M) Util %

Vote Allocation by Financing Source

LKR Millions

Treasury Imprest Reconciliation

BoC A/C #704210 · FR 135 / FR 394

Bank of Ceylon (#704210) Imprest & CIGAS Voucher Register

Click any voucher row to inspect FR 135 certification or reconcile unpresented cheques
Voucher No. Date Payee / Beneficiary Object Source Cheque / Ref Amount (LKR) Status

Multi-Agency Procurement & Dual Compliance Register

Sri Lanka National Procurement Guidelines 2006 (DPC / MPC) × IUCN / GEF Prior Review Thresholds
Total Contract Portfolio
$1,102,000
10 Core Seascape Packages
Commitment Rate
93.9%
Against $1,174,000 Puttalam BAC
National Guidelines 2006
9 / 10 Cleared
DPC & MPC Approvals Logged
IUCN / GEF Prior Review
6 / 6 Cleared
No-Objection & ESMS Compliant
Package ID Contract Package Title Agency Method NPG 2006 Authority IUCN / GEF Tier Contract ($) Paid % Status
Select any contract package to inspect technical specifications, TEC/MPC/DPC clearances, IUCN prior-review No-Objection letters, and payment milestones.

Multi-Donor Disbursement Tracker & UN-SEEA / PES Linkage

GEF STAR vs 7-Agency Co-Financing · Puttalam Supply & Use Table (GEP) · Revolving PES Simulator

Co-Financing & GEF STAR Disbursement Ledger

Puttalam Allocation: $1.17M GEF STAR + $7.29M Counterpart (7 Agencies)
Funding Agency / Source Modality Pledged ($) Mobilised ($) Delivery %

Agency Contribution Comparison

Pledged vs Mobilised (USD Thousands)

UN-SEEA Supply & Use Table (SUT) — Puttalam

Experimental Ecosystem Accounts (DCS & CBSL)
GEP: LKR 8,338.3M / yr
Ecosystem Service / Asset Primary User Sector Physical Flow Value (LKR M/yr)
Gross Ecosystem Product (GEP — Puttalam Lagoon & Coast) 8,338.3

Blue carbon ecosystems (mangroves, seagrass meadows, salt marshes) sequester carbon at 2–4× the rate of terrestrial tropical forests whilst buffering cyclones and sustaining lagoon fisheries.

PES Revolving Fund Simulator

Supporting 300 Fisher Families & Mangrove Nurseries
Annual PES Pool
$153,750 / yr
LKR 46.13M / yr
Per Fisher Family (300 HH)
$256 / yr
50% Livelihood Co-Management
Community Mangrove Nurseries
$46,125 / yr
30% Allocation · ~115 ha/yr
Bar Reef & Lagoon Enforcement
$30,750 / yr
20% Allocation · Fuel & Telemetry
Action completed.