GEF-7 Project ID 10552 · Annex 1 Executive Monitoring Cycle · Ministry of Environment (Head 160)

Puttalam Lagoon & Barrier Estuary Seascape (294,822 ha)

Monthly portfolio stewardship console integrating Earned Value Management, WBS physical milestones, procurement compliance, multi-donor liquidity, GOSL Treasury Vote PFM reconciliation, and SEEA-EA Natural Capital Accounts.

Fixed Treasury Exchange Rate: 300 LKR / USD · 4 DSDs: Puttalam, Kalpitiya, Mundel, Vanathavillu
Monitoring Cycle Inspector (48-Month Horizon)
Month 24 · Year 2 (Q4) Current Executive Baseline
M1 (Y1 Start) M12 (Y1 Close) M24 (Y2 Baseline) M36 (Y3 Close) M48 (Terminal)
Seascape Extent Baseline
294,822 ha
131,615 ha Terrestrial · 163,207 ha Marine/Lagoon
Total Portfolio & 2027 Vote
$8.46M
2027 Vote (Head 160): LKR 534.70M ($1.78M)
Physical Progress (M24)
47.7%
EV: $4.04M vs PV: $4.29M
Earned Value Indices
SPI 0.94 · CPI 1.02
AC: $3.96M · Slight Schedule Lag
GEF STAR & Cash Runway
$497k (42.3%)
4.8 mo Runway · Next Imprest Due

Executive Monitoring Snapshot & Seascape Spatial Profile

Integrated performance trajectory across Earned Value (PV, EV, AC), critical coastal ecosystem assets, and Divisional Secretariat Division (DSD) intervention zones.

M24 · Active Implementation

48-Month Earned Value Trajectory (PV, EV & AC)

Cumulative Portfolio Value (USD Millions)
CV: +$79k Favourable · SV: -$258k

Puttalam Seascape Habitat & DSD Schematic

Click any zone or DSD to inspect site baseline
Bar Reef Sanctuary 6,314 ha Coral Reefs Seagrass 24,068 ha Kala Oya Estuary 1,741 ha Mangroves (600 ha Rest.) Mee Oya Estuary Kalpitiya DSD Vanathavillu DSD Puttalam DSD Mundel DSD 7.75°N–8.30°N, 79.81°E · 8 Lagoon Islands (Battalangunduwa)
Active Selection: Entire Puttalam Seascape (294,822 ha) — 1,741 ha mangroves, 24,068 ha seagrass meadows, 6,314 ha coral reefs (Bar Reef, Talawila, Kandakuliya). Click any map label to inspect DSD/habitat details.

Divisional Secretariat Extent & Habitat Matrix

Divisional Secretariat / Marine Zone Terrestrial (ha) Marine / Lagoon (ha) Total Extent (ha) Primary Intervention Focus
Puttalam DSD 17,840 — 17,840 IIDSS Hub, Salterns & SEEA Urban/Lagoon Buffer
Kalpitiya DSD 15,875 — 15,875 PES Eco-Tourism Surcharge ($3/night), Seaweed Farming
Mundel DSD 24,145 — 24,145 Mundel Lake (3,040 ha) & Aquaculture Effluent Control
Vanathavillu DSD 73,755 — 73,755 Kala Oya Estuary (600 ha Mangrove Restoration)
Marine, Lagoon & Dutch Bay Zone — 163,207 163,207 Bar Reef Demarcation (6,314 ha) & Seagrass (24,068 ha)
Total Puttalam Seascape 131,615 163,207 294,822 44.6% Terrestrial / 55.4% Marine & Lagoon

Executive Action Flags & Cross-Domain Alerts

Schedule Performance (SPI = 0.94)
Hydrological dredging permit lag at Kala Oya Sector B (-6% vs planned M24).
Monitor
GEF Operational Cash Runway (4.8 Months)
Imprest replenishment request ($280k) scheduled for IUCN review prior to M26.
Replenish
Procurement Commitment Rate (98.5%)
$915,620 contracted across all 10 Annex 1 packages; $14,300 net bid savings.
Compliant
Bank of Ceylon A/C #704210 Reconciliation
Head 160 Vote LKR 534.70M · TOD Imprest & Vouchers reconciled with zero variance.
Verified
SEEA-EA Gross Ecosystem Product Baseline
LKR 8,338.3M ($27.79M/yr) codified; PES fund projects LKR 141.6M/yr revenue.
Published

Domain A · Work Breakdown Structure (WBS) & Physical Milestones

Multi-tier breakdown across Component 1 (Policy, SEEA Accounts, IIDSS, MSP, PES, Capacity) and Component 2 (600 ha Mangrove Restoration, 300 Fisher Families Aquaculture, Bar Reef Demarcation, M&E, Blue Bond Pipeline).

WBS Code & Deliverable Lead Agency Physical Target Allocated Budget Completion % Status Flag

Domain B · Procurement & Contract Management Register

Tracking all 10 Annex 1 procurement packages ($929,920 budget; $915,620 contracted / 98.5% commitment rate) across IUCN/GEF prior & post review compliance and MPC/DPC approval stages.

Annex 1 Procurement Budget
$929,920
10 Approved Packages
Total Contracted Value
$915,620
98.5% Commitment Rate
Procurement Variance (Savings)
$14,300
1.5% Below Engineer Estimate
IUCN / GEF Prior Review
5 of 10 Packages
100% No-Objection Cleared
Package ID & Description Category Method GEF Review MPC / DPC Stage Budget Contracted Commit %

Domain C · Multi-Donor Disbursement & Liquidity Tracker

GEF STAR Grant ($1.17M allocated, $497k disbursed / 42.3%, 4.8-month runway) alongside $7.29M counterpart co-financing across 7 line agencies and academic partners.

Cumulative Disbursement S-Curve (M1–M48)

GEF STAR & Co-Financing Cumulative Mobilisation

Monthly Burn Rate & Imprest Cash Runway

Monthly GEF Cash Outflow vs Replenishment Buffer

Co-Financing & Donor Realisation Schedule (7 Line Agencies + GEF STAR)

Pledged vs Realised as of Month 24
Operational Runway: 4.8 Months ($156k Liquid Imprest)
Funding Partner / Line Agency Modality Co-Financing Window Pledged / Allocated Disbursed / Realised Realisation % Compliance Status

Domain D · GOSL Treasury Vote & PFM Compliance Ledger

Ministry of Environment — Head 160, Programme 02, Project 04 (2027 Parliamentary Budget Estimates: LKR 534.70M), Treasury Operations Department (TOD) imprest releases, passed vouchers, and Bank of Ceylon A/C #704210 reconciliation.

PFM Audit Status: Reconciled · Zero Variance
2027 Parliamentary Vote (Head 160)
LKR 534.70M
Prog. 02 · Project 04
TOD Imprest Releases (YTD)
LKR 265.00M
49.6% of Annual Estimate Released
Passed Vouchers Expended
LKR 253.90M
95.8% Imprest Utilisation
Unexpended Vote Balance
LKR 280.80M
LKR 42.60M Encumbered POs

2027 Vote Expenditure by Treasury Object Code

Budget Estimate vs YTD Passed Vouchers
Object Code Classification Description 2027 Vote YTD Expended Unexpended Util. %

Bank of Ceylon A/C #704210 Reconciliation

Monthly Treasury & Operating Account Statement

Recent TOD Imprest & Passed Voucher Register

Voucher / TOD Ref Code Amount Status

Domain E · SEEA Ecosystem Accounts & PES Revolving Fund Simulator

Spatial extent & condition baselines, Supply and Use Table (SUT) generating LKR 8,338.3M ($27.79M) in annual Gross Ecosystem Product, and an interactive Payment for Ecosystem Services (PES) financial model.

Gross Ecosystem Product: LKR 8,338.3M / yr ($27.79M)

SEEA-EA Spatial Extent & Condition Account

Ecosystem Asset Type Extent (ha) Condition Index Annual Service Flow

Supply & Use Table (SUT) — Annual GEP Breakdown

SEEA Service Category Primary Economic Beneficiaries Annual Value Share %

Interactive PES Revolving Fund Financial Simulator

Model conservation surcharges and aquaculture effluent levies to sustain community restoration stipends (LKR 72.0M/yr) and marine patrol boats.

Default $3.00/night across Kalpitiya resorts & eco-lodges
Baseline: 120,000 visitor-nights/yr
Default $15/ha across 7,467 ha licensed coastal aquaculture footprint
300 families = LKR 72.0M/yr community stewardship payroll
LKR 17.4M/yr per vessel (crew, fuel, telemetry & Bar Reef buoy upkeep)
Annual PES Revenue
LKR 141.60M
Tourism 76% · Effluent 24%
Conservation Outflows
LKR 121.00M
Stipends 72.0M · Patrols 34.8M
Net Revolving Surplus
+LKR 20.60M
Self-Sustaining (14.5% Reserve)